Claim Review Against the Record
Every claimed item traced to the specifications, tender documents, bid clarifications, meeting minutes and correspondence — separating scope that was already bought from genuine extras before anyone negotiates.
A claim stops a project twice — once when the work stops, and again when the argument starts. Most claims mix genuine extras with scope that was already bought; the fastest way back to work is to separate the two on the record, then solve the commercial problem underneath.
In 2009, four months into fabrication of advanced equipment for a Saudi manufacturing facility, the selected supplier stopped work and claimed USD 600,000 on a USD 900,000 order. This practice had written the specifications, tender documents and technical bid evaluation, and checked each of the 30+ claimed extras against that record: only USD 12,000 was genuinely new scope. The real cause was an underpriced bid, so the settlement paid only what was legitimate or commercially justified — USD 93,000, agreed in two working days and split so the client could approve it without a lengthy board process. Fabrication restarted with the specified equipment, and no international dispute followed.
Every claimed item traced to the specifications, tender documents, bid clarifications, meeting minutes and correspondence — separating scope that was already bought from genuine extras before anyone negotiates.
Technical and cost assessment of change orders and variations: what the contract already covers, what is genuinely new, and what a fair adjustment looks like.
Why the work really stopped — an underpriced bid, a design change, late information or a supply disruption — and a recovery path that restarts fabrication or construction, not just a position paper.
A reasoned settlement the client can approve, structured around its approval limits where needed, and support at the table in Arabic, French or English.
A written, independent opinion on disputed scope, defects or damage in tank farm, terminal and pipeline projects — for owners, contractors, insurers or counsel.
Specifications, tender documents and technical bid evaluations written to hold up later — the same record that settled the 2009 claim in two days.
Engagements run project-based (defined scope and deliverables), as a standing technical advisory retainer, or start small with a fixed-scope audit — see engagement models.
Separating facts from positions. Each claimed item is traced to the specification, the bid, the clarifications and the correspondence, so both sides can see which items were already in scope and which are genuinely new. The commercial problem underneath — often an underpriced bid or a disrupted supply chain — is then settled on terms the client can approve. In the 2009 Saudi case, that took two working days.
For one party per matter, after a conflict check — never both sides of the same dispute. Owners engage the review to answer a claim; EPC contractors and suppliers engage it to test a claim before submitting it. The independence is structural: no vendor commissions and no stake in the outcome.
No — the aim is to settle the dispute early, on the record, before it becomes formal. Where a matter is already in arbitration or court, the same item-by-item analysis can support counsel as an independent technical opinion on scope, defects or damage in tank farm, terminal and pipeline assets.
The contract or purchase order, the specifications and tender documents, the bid and its clarifications, the claim and the correspondence. A first written assessment of the claim's structure — what looks like existing scope and what needs negotiating — follows within 10 working days of a complete file.
A short description of your facility and challenge is enough to start. You'll get a discovery call invitation and an initial qualification questionnaire — available worldwide.