Technical mediation & supplier claims review.

A claim stops a project twice — once when the work stops, and again when the argument starts. Most claims mix genuine extras with scope that was already bought; the fastest way back to work is to separate the two on the record, then solve the commercial problem underneath.

USD 93k
Settled on a USD 600k claim
-84.5%
Claim reduction
2 days
To agreement
30+
Claimed items checked

Why it matters.

In 2009, four months into fabrication of advanced equipment for a Saudi manufacturing facility, the selected supplier stopped work and claimed USD 600,000 on a USD 900,000 order. This practice had written the specifications, tender documents and technical bid evaluation, and checked each of the 30+ claimed extras against that record: only USD 12,000 was genuinely new scope. The real cause was an underpriced bid, so the settlement paid only what was legitimate or commercially justified — USD 93,000, agreed in two working days and split so the client could approve it without a lengthy board process. Fabrication restarted with the specified equipment, and no international dispute followed.

Scope of service

What this service covers.

01

Claim Review Against the Record

Every claimed item traced to the specifications, tender documents, bid clarifications, meeting minutes and correspondence — separating scope that was already bought from genuine extras before anyone negotiates.

02

Change-Order & Variation Assessment

Technical and cost assessment of change orders and variations: what the contract already covers, what is genuinely new, and what a fair adjustment looks like.

03

Root Cause & Project Recovery

Why the work really stopped — an underpriced bid, a design change, late information or a supply disruption — and a recovery path that restarts fabrication or construction, not just a position paper.

04

Settlement Design & Negotiation Support

A reasoned settlement the client can approve, structured around its approval limits where needed, and support at the table in Arabic, French or English.

05

Independent Technical Opinion

A written, independent opinion on disputed scope, defects or damage in tank farm, terminal and pipeline projects — for owners, contractors, insurers or counsel.

06

Dispute Avoidance from the Tender

Specifications, tender documents and technical bid evaluations written to hold up later — the same record that settled the 2009 claim in two days.

Codes & standards

Judged against the contract record and the codes it cites.

Purchase-order & tender documentsBid clarifications & minutesAPI 650 / 653ASME B31.3 / B31.4NFPA 30 / 11
Who this is for

Built for owners, operators and their partners.

  • Owners and project companies facing a supplier or contractor claim mid-project
  • EPC contractors and suppliers who want a claim tested before they submit it — or before they pay one
  • Claims consultants, insurers and counsel needing technical depth on storage, terminal or pipeline scope

Engagements run project-based (defined scope and deliverables), as a standing technical advisory retainer, or start small with a fixed-scope audit — see engagement models.

Download the capability statement (PDF)

FAQ

Common questions about this service.

What does technical mediation involve in a supplier or contractor dispute?

Separating facts from positions. Each claimed item is traced to the specification, the bid, the clarifications and the correspondence, so both sides can see which items were already in scope and which are genuinely new. The commercial problem underneath — often an underpriced bid or a disrupted supply chain — is then settled on terms the client can approve. In the 2009 Saudi case, that took two working days.

Do you act for the owner or for the contractor?

For one party per matter, after a conflict check — never both sides of the same dispute. Owners engage the review to answer a claim; EPC contractors and suppliers engage it to test a claim before submitting it. The independence is structural: no vendor commissions and no stake in the outcome.

Is this arbitration or expert-witness work?

No — the aim is to settle the dispute early, on the record, before it becomes formal. Where a matter is already in arbitration or court, the same item-by-item analysis can support counsel as an independent technical opinion on scope, defects or damage in tank farm, terminal and pipeline assets.

What do you need to start a claims review?

The contract or purchase order, the specifications and tender documents, the bid and its clarifications, the claim and the correspondence. A first written assessment of the claim's structure — what looks like existing scope and what needs negotiating — follows within 10 working days of a complete file.

Next step

Describe the asset — get a scoped approach back.

A short description of your facility and challenge is enough to start. You'll get a discovery call invitation and an initial qualification questionnaire — available worldwide.