Specifications & Tender
Technical specifications, tender documents and technical bid evaluation across seven suppliers — the record the dispute was later settled on.
Technical-commercial mediation of a supplier's USD 600,000 claim on a USD 900,000 equipment order — settled at USD 93,000 in two working days, with fabrication restarted and the specified equipment kept.
Case study published 21 October 2026
Specifications · Tender & Bid Evaluation · Claim Review · Negotiation
Technical specifications, tender documents and technical bid evaluation across seven suppliers — the record the dispute was later settled on.
Each of the 30+ claimed additional items checked against the specifications, bid clarifications, meeting records and correspondence.
Commercial review of why the supplier stopped work: a bid priced below what the specified components cost, not a change of scope.
A reasoned USD 93,000 accommodation, split so the client could approve it without a lengthy board process.
The negotiation took place in a third country, with the client's management in the room. Eng. Naim brought the specifications, bid clarifications, meeting records, correspondence and written confirmations from the supplier's former project manager, and went through the supplier's 30+ claimed items one by one. Almost all had been explicitly included or resolved during bidding and clarification; only USD 12,000 was accepted as genuinely additional, and the supplier acknowledged that the scope issues were settled. The supplier then admitted that its former project manager had badly underestimated the manufacturing cost. The specified components were among the best on the market and the original bid had been unusually low, so simply enforcing the price risked a longer suspension and greater exposure for the client. Eng. Naim proposed a USD 93,000 accommodation: the USD 12,000 legitimate item plus USD 81,000 of commercially justified support. The client could approve only USD 40,000 as a contract variation without a lengthy board process, so he split it — USD 40,000 as a variation and USD 53,000 as separately defined additional works. The full USD 93,000 was agreed and approved, bringing the order to about USD 993,000.
Winning the scope argument was not enough to finish the project. The supplier's real problem was an underpriced bid, so the settlement paid only for what was legitimate or commercially justified — and was structured so the client could approve it quickly.
The supplier's USD 600,000 demand settled at USD 93,000 — 84.5% less, limiting the increase to about 10.3% of the original order.
Agreement reached in two intensive working days; fabrication resumed and the schedule was protected.
The high-performance equipment chosen in the tender was preserved — no re-tender and no replacement supplier.
Escalation into a costly cross-border contract dispute was avoided.
The services behind this project, explained in depth.
Send the brief — Eng. Naim replies personally with a discovery-call invitation and a short qualification questionnaire.