Tank Farm Layout & Spacing Studies
Plot development to NFPA 30 / API spacing rules — tank-to-tank and tank-to-boundary distances, bund and dike sizing, road and access planning, drainage philosophy and future expansion headroom.
Tank farms are designed once and lived with for forty years. Layout, spacing, bunding, venting and accessory choices made at the design stage determine the facility's safety case, its maintenance bill and its expansion headroom for decades.
This practice has engineered more than 500,000 m³ of storage — from the 27-tank modernization of the SAMIR refinery tank farm in Morocco (individual tanks to 45,000 m³) to the 13-tank revamp and expansion of IPT Terminal in Lebanon, and a tank de-watering design adopted as a Saudi Aramco standard. New construction, rehabilitation of ageing fleets, and independent review of contractor designs are all routine scopes.
Plot development to NFPA 30 / API spacing rules — tank-to-tank and tank-to-boundary distances, bund and dike sizing, road and access planning, drainage philosophy and future expansion headroom.
API 650 / API 620 design basis, shell and roof configuration selection, nozzle orientation, foundation interface loads, venting per API 2000 and complete mechanical datasheets for procurement.
Inspection-led assessment of ageing tanks converted into a prioritized, executable repair scope — shell, bottom, roof, seals and accessories — in the discipline of API 653.
Pressure-vacuum valves, gauging and overfill protection, blanketing systems, and automated de-watering — including the design adopted as a standard requirement across Saudi Aramco's tank fleet.
Independent review of contractor and vendor tank designs — calculations, drawings and material documentation checked against codes and the owner's interest before steel is ordered.
Fabrication-drawing review, multi-site construction supervision, hydrotest witnessing, punch-listing and documented handover — as delivered across 27 tanks at SAMIR.
Engagements run project-based (defined scope and deliverables), as a standing technical advisory retainer, or start small with a fixed-scope audit — see engagement models.
API 650 and API 620 for design, API 653 for assessment and rehabilitation, API 2000 for venting, NFPA 30 for spacing and containment, and EN 14015 where European practice governs. Saudi Aramco SAES requirements are routine from years inside Aramco design programmes.
Both. The SAMIR programme combined rehabilitation and new construction across 27 tanks, and the IPT engagement rehabilitated nine existing tanks while adding four new ones. Rehabilitation scopes start from inspection findings and are prioritized by safety and operational impact.
Yes — owner-side design review is a standing service. Calculations, fabrication drawings, material documentation and test reports are checked against the applicable codes and the contract, with exceptions reported before they become field problems.
Layout and spacing, mechanical datasheets and calculations, foundation interface loads, piping and manifold arrangement, bund and drainage design, firefighting interface, electrical and instrumentation scope, and material take-off — coordinated as one package so procurement and construction work from a consistent picture.
A short description of your facility and challenge is enough to start. You'll get a discovery call invitation and an initial qualification questionnaire — available worldwide.