Skip to main content
All servicesSpecialist Service

Firefighting system design for tank farms & fuel terminals.

Tank farm fire protection is the one system an operator buys hoping never to use — and the one where a design shortfall is unaffordable. Scenario definition, foam application rates, water demand and pumping reliability have to be engineered against the worst credible fire, not the most convenient one.

NFPA 30 · 11 · 20
Design basis
AFFF + FP
Dual-foam architecture
27 tanks
SAMIR FF upgrade scope
13 tanks
IPT system delivered

Why it matters.

This practice designs firefighting systems beyond NFPA and API minimums where the risk justifies it: the IPT Terminal system combines dual foam agents (AFFF and fluoroprotein) with fixed protection and long-range monitors, delivered through testing, commissioning, standing instructions and operator training. At SAMIR, the refinery's firefighting infrastructure was upgraded to current international standards across a 27-tank facility — coordinated with live operations throughout.

Scope of service

What this service covers.

01

Fire Scenario & Demand Definition

Credible-scenario analysis — full-surface tank fire, rim-seal fire, bund fire — converted into foam and cooling-water demand calculations the system is actually sized against.

02

Foam System Design (NFPA 11)

Foam concentrate selection, proportioning, foam chambers and pourers, and long-range monitors for bunded areas — including dual-agent (AFFF / fluoroprotein) architectures for mixed open and closed hazards.

03

Fire Water Networks & Tank Cooling

Ring mains, hydrant and monitor coverage, tank cooling arrangements and network hydraulics — engineered so the demand case is met at the furthest, highest nozzle.

04

Fire Pumps & Emergency Power

Fire pump station design to NFPA 20 plus the discipline most designs miss: generator sizing for firefighting duty and large-motor starting, specification, earthing and protection.

05

Detection, Alarm & Interface

Detection philosophy, alarm and control interfaces, and coordination with drainage so firewater and fuel are managed — not just discharged — during an event.

06

Upgrades, Testing & Training

Upgrading live facilities without leaving them unprotected mid-works; performance testing, commissioning, standing instructions and hands-on operator training at handover.

Codes & standards

Designed to the standards your regulator reads.

NFPA 30NFPA 11NFPA 20API RP 2021Local civil-defense codesISO
Who this is for

Built for owners, operators and their partners.

  • Tank farm and terminal operators upgrading legacy fire protection
  • Owners whose insurers or regulators have raised the bar on fire systems
  • EPCs needing a senior fire-protection design discipline on a storage project

Engagements run project-based (defined scope and deliverables), as a standing technical advisory retainer, or start small with a fixed-scope audit — see engagement models.

Download the capability statement (PDF)

FAQ

Common questions about this service.

Which codes govern tank farm firefighting design?

NFPA 30 for the flammable-liquids facility itself, NFPA 11 for foam systems, NFPA 20 for fire pumps, with API RP 2021 informing tank-fire response — plus whatever the local civil-defense authority requires. Where the risk justifies it, we design beyond the code minimum, not to it.

Can fire protection be upgraded while the facility keeps operating?

Yes, with sequencing discipline: the SAMIR firefighting upgrade ran across a live refinery tank farm for three years, coordinated with operations and HSE so protection was maintained throughout the works.

How is the foam agent chosen?

By hazard: product class, tank type, open versus closed areas and environmental constraints. The IPT design used a dual-agent architecture — AFFF and fluoroprotein — matched to different areas of the same terminal, rather than forcing one agent to cover everything.

Do you also size the fire pumps and their power supply?

Yes — including the part that is often missed: emergency generator sizing for firefighting duty with large-motor starting loads, plus specification, protection and earthing. Power generation engineering is a core discipline of the practice.

Next step

Describe the asset — get a scoped approach back.

A short description of your facility and challenge is enough to start. You'll get a discovery call invitation and an initial qualification questionnaire — available worldwide.