Full construction supervision of the rehabilitation and new construction of 27 storage tanks of different sizes and types, with individual capacities up to 45,000 m³.
Multi-year modernization of tank farms, loading/unloading facilities and firefighting system — 27 tanks rehabilitated or newly built (up to 45,000 m³ each).
Case study published 18 May 2026 · Last reviewed 20 May 2026
Full construction supervision of the rehabilitation and new construction of 27 storage tanks of different sizes and types, with individual capacities up to 45,000 m³.
Supervision of the modernization works on product loading and unloading infrastructure — raising throughput capacity and operational efficiency.
Supervision of the upgrade of the refinery firefighting infrastructure to meet international safety standards.
On-site engineering coordination across the multidisciplinary scope, ensuring compliance with design, codes and refinery operational constraints throughout the works.
The programme operated under sustained on-site engineering presence over three years, providing continuity of technical oversight from start to handover. Tank works were sequenced around live refinery operations, firefighting upgrades were coordinated with operations and HSE, and loading/unloading modifications were tied into existing infrastructure with minimum disruption. The discipline of multi-year on-site coordination is what allowed a scope of this size — 27 tanks and three operationally critical systems — to be delivered against the refinery's strategic schedule.
Rehabilitation and new construction of 27 tanks of varying sizes and types, with combined capacity exceeding 500,000 m³ across the modernised tank farm.
Facility firefighting infrastructure brought in line with current international safety standards — materially improved protection of personnel, assets and the surrounding environment.
Modernised loading and unloading facilities delivered higher throughput and operational efficiency, supporting the refinery's wider production and dispatch programme.
Prepared an operational philosophy for upgrading oil movements to prevent product contamination during transfer. A set of minor modifications produced large quality improvements, especially for sensitive low-sulphur products.
Prepared an operational philosophy for optimal storage-tank usage, with recommended piping modifications for refined products so each grade flows through the right route and the right tank.
Process flow diagrams reissued in line with the modernised operating regime, giving operations a current reference for day-to-day decisions.
Sustained construction supervision and engineering coordination across a three-year programme — continuity of technical oversight from start to handover.