Fuel TerminalLebanon

Rehabilitation of Jirco Terminal

Fast-track 3-month terminal rehabilitation — inspection, scope definition, supervision of works and commissioning / start-up across all systems.

Case study published 20 May 2026

Location
Dora, Lebanon
Duration
3 months
End Client
Jirco
Role

Inspection · Scope Definition · Supervision · Commissioning

3 mo
Fast-track
Full
Systems re-commissioned
Min
Operational downtime
Project Background

The context that shaped the engineering.

The Jirco terminal at Dora needed a rapid, disciplined rehabilitation to restore operational reliability without the extended downtime of a full rebuild. The objective was a fast-track engagement: inspect, decide, fix, recommission — in three months, with all terminal systems back online and a maintenance plan in place to protect what had been restored.
Scope of Services

What was delivered.

01

Terminal Inspection

End-to-end inspection of mechanical, piping, instrumentation and ancillary terminal systems.

02

Scope Definition

Prioritised maintenance scope built around the fast-track timeline — focus on items affecting safety, throughput and reliability.

03

Supervision of Works

On-site supervision of the rehabilitation works through to mechanical completion.

04

Commissioning & Start-up

Pre-commissioning checks, performance verification, system-by-system start-up and operational handover.

05

Long-Term Maintenance Plan

Documented preventive-maintenance routine to protect the rehabilitation investment going forward.

Design Solution

How the engineering came together.

Integrated multidisciplinary delivery

A three-month programme of this scope only works if scoping discipline is tight. Inspection findings were converted into a ranked list of items, items below the safety/throughput threshold were deferred to the maintenance plan rather than allowed to expand the construction scope, and execution was sequenced so that commissioning could begin in parallel with the tail of the works. The result was a terminal back online inside the fast-track window with a maintenance routine in place to prevent regression.

Key Outcomes

The results the client took to operations.

Fast-Track Delivery

Full rehabilitation delivered in three months — minimising operational downtime for the operator.

All Systems Recommissioned

Successful commissioning and start-up across all terminal systems before handover.

Ongoing Reliability Plan

Maintenance routine handed to operations — protecting the rehabilitation investment going forward.

Disciplines Covered

Multidisciplinary by design.

MechanicalPipingInstrumentation & ControlInspectionConstruction SupervisionCommissioning & Start-upMaintenance Engineering
Need this capability?

The services behind this project, explained in depth.

Your project

Have a similar engineering problem on your asset?

Send the brief — Eng. Naim replies personally with a discovery-call invitation and a short qualification questionnaire.