Power GenerationLebanon

EDL Power Station Fuel Sea Lines — Operations & Maintenance

Six-year operations and maintenance of the 20" and 6" fuel-oil sea lines feeding the Zouk power station — sustaining 700,000+ tons of annual product discharge with zero environmental incidents.

Case study published 20 May 2026

Location
Zouk, Lebanon
Duration
6 years
End Client
Électricité du Liban (EDL)
While At
Falcon / Conapro
Role

Operations & Maintenance Support · Engineering Supervision

700,000+ t/yr
Discharged
Zero
Environmental incidents
6 yrs
Continuous service
20" + 6"
Sea lines
Project Background

The context that shaped the engineering.

The Zouk power station is one of Lebanon's principal electricity generation facilities, dependent on a continuous fuel oil supply landed through sea lines and offloaded from tankers. The integrity of the 20" and 6" sea-line system — and the routines that maintain it — directly conditions the station's ability to generate power for the national grid. The objective of the six-year engagement was to operate and maintain the sea-line system to a safety and environmental standard appropriate for the volumes handled, while extending the lifespan of the underlying assets through disciplined preventive maintenance.
Scope of Services

What was delivered.

01

Sea-Line Operations Support

Operational oversight of the 20" and 6" fuel-oil sea lines, supporting discharge of more than 700,000 tons/year of oil products.

02

Periodic Maintenance Supervision

Replacement of motorised valves and associated control panels, replacement of 6" and 20" flexible hoses on scheduled intervals.

03

Cathodic Protection Upgrade

Installation of a new cathodic protection system to safeguard pipeline integrity against marine corrosion over the long term.

04

HSE Discipline

Operations and maintenance routines designed to deliver continuous discharge with zero environmental incidents through the service period.

Design Solution

How the engineering came together.

Integrated multidisciplinary delivery

The engagement was structured around a preventive maintenance philosophy rather than reactive intervention. Valve and hose replacements were scheduled to anticipate degradation rather than failure, the cathodic protection upgrade was sized for long-term marine exposure rather than minimum compliance, and operations supervision was set up to detect and act on anomalies early. The result was multi-year continuous service with environmental performance treated as a hard constraint, not a target.

Key Outcomes

The results the client took to operations.

Reliable Discharge

700,000+ tons of fuel oil discharged each year with zero environmental incidents across the six-year programme.

Asset Lifespan Extension

Preventive-maintenance programme extending the operating life of motorised valves, hoses and sea-line accessories.

Long-Term Integrity

Upgraded cathodic protection system safeguarding sea-line integrity against marine corrosion.

Disciplines Covered

Multidisciplinary by design.

MechanicalPipingPipeline EngineeringCathodic ProtectionMarine / Sea-Line OperationsMaintenance EngineeringHSE