Khurais Upstream Facilities — Detailed Design

Multidisciplinary detailed engineering for the Khurais upstream development — 14 oil manifolds, 237 oil wells and 144 water-injection wells with combined flow- and trunk-line networks of about 1,390 km.

Case study published 20 May 2026 · Last reviewed 22 May 2026

Location
Khurais Field, KSA
Duration
18 months
End Client
Saudi Aramco
While At
Khatib & Alami
Role

Mechanical / Piping Engineer

14
Oil manifolds
237
Oil wells
144
Water-injection wells
~1,390 km
Pipe network
Project Background

The context that shaped the engineering.

Khurais is one of the world's largest oil fields and a strategic upstream development for Saudi Aramco. The scope brought together oil production, gathering, manifolding and water-injection infrastructure into a single coordinated engineering package — sized to feed downstream processing while supporting reservoir pressure through water injection.
Scope of Services

What was delivered.

01

PFDs & P&IDs

Process flow diagrams and piping & instrumentation diagrams across manifolds, flowlines and water-injection laterals.

02

Datasheets & Material Take-Off

Equipment, valve and line datasheets with full material take-off for procurement.

03

Routing & Plan/Profile

Flowline and trunk-line routing verification, plan and profile drawings for the field-wide network.

04

Chemical Injection & Hydraulics

Chemical injection rate calculation and hydraulic analysis for trunk and gathering systems up to 36".

05

Piping Plans, Details & Isometrics

Piping plans, details and isometrics across the manifolds and well-tie-in areas.

Design Solution

How the engineering came together.

Integrated multidisciplinary delivery

The challenge of Khurais at the detail-engineering level was coordination at scale: hundreds of well-tie-ins, fourteen manifolds and a water-injection grid all sharing right-of-way and operational philosophy with the oil-gathering network. The deliverables were engineered as a single coordinated set — same datums, same hydraulic basis, same chemical-injection strategy — so the procurement and construction teams downstream could execute against a consistent picture of the field.

Key Outcomes

The results the client took to operations.

Coordinated Field-Wide Package

14 oil manifolds, 237 oil wells and 144 water-injection wells engineered into one consistent design package.

Procurement-Ready Deliverables

Full PFDs, P&IDs, datasheets, isometrics and material take-off — ready for procurement and field execution.

Reservoir-Aware Engineering

Water-injection infrastructure engineered in step with oil-gathering so reservoir pressure management is part of the original design, not a retrofit.

Disciplines Covered

Multidisciplinary by design.

MechanicalPipingPipeline EngineeringProcessHydraulicsField Development Engineering
Your project

Have a similar engineering problem on your asset?

Send the brief — Eng. Naim replies personally with a discovery-call invitation and a short qualification questionnaire.