Multidisciplinary detailed engineering for the Khurais upstream development — 14 oil manifolds, 237 oil wells and 144 water-injection wells with combined flow- and trunk-line networks of about 1,390 km.
Case study published 20 May 2026 · Last reviewed 22 May 2026
Mechanical / Piping Engineer
Process flow diagrams and piping & instrumentation diagrams across manifolds, flowlines and water-injection laterals.
Equipment, valve and line datasheets with full material take-off for procurement.
Flowline and trunk-line routing verification, plan and profile drawings for the field-wide network.
Chemical injection rate calculation and hydraulic analysis for trunk and gathering systems up to 36".
Piping plans, details and isometrics across the manifolds and well-tie-in areas.
The challenge of Khurais at the detail-engineering level was coordination at scale: hundreds of well-tie-ins, fourteen manifolds and a water-injection grid all sharing right-of-way and operational philosophy with the oil-gathering network. The deliverables were engineered as a single coordinated set — same datums, same hydraulic basis, same chemical-injection strategy — so the procurement and construction teams downstream could execute against a consistent picture of the field.
14 oil manifolds, 237 oil wells and 144 water-injection wells engineered into one consistent design package.
Full PFDs, P&IDs, datasheets, isometrics and material take-off — ready for procurement and field execution.