Scraper Launcher & Receiver Facilities — Hawtah HEW 3-1 Pipeline

Project management of new scraper launcher and receiver facilities on the Saudi Aramco HEW 3-1 pipeline — P&IDs, layouts, piping, grading, structural, instrumentation, electrical and full procurement-ready deliverables.

Case study published 20 May 2026 · Last reviewed 10 June 2026

Location
Hawtah Area, KSA
Duration
6 months
End Client
Saudi Aramco
While At
Khatib & Alami
Role

Project Manager

PM
Project Manager
HEW 3-1
Pipeline
6 mo
Programme
Multi-disc.
Deliverables
Project Background

The context that shaped the engineering.

Pigging — the routine cleaning and inspection of pipelines using scrapers — is part of the long-term integrity management of any major crude pipeline. The Hawtah HEW 3-1 pipeline needed dedicated launcher and receiver facilities so the operations team could pig the line on schedule without disrupting throughput. The project objective was to deliver a complete, build-ready package for those facilities in a focused six-month programme.
Scope of Services

What was delivered.

01

Project Management

Programme management of the launcher/receiver design scope through to procurement-ready deliverables.

02

Multidisciplinary Design

P&IDs, plot plan, piping, grading, structural, instrumentation and electrical drawings.

03

Datasheets & Project Text

Equipment datasheets and project text supporting the technical scope.

04

Material Take-Off

Material take-off for procurement of mechanical, piping, structural, instrumentation and electrical scope.

Design Solution

How the engineering came together.

Integrated multidisciplinary delivery

The package was sized to be procurement-ready at the end of the six-month programme — meaning the technical, structural and material deliverables had to line up cleanly with one another and with the surrounding pipeline. Project management discipline kept the multidisciplinary scope tracking on a single schedule, so launcher and receiver could be built and tied in without iterations between disciplines after the design phase closed.

Key Outcomes

The results the client took to operations.

Pigging Capability for HEW 3-1

Dedicated launcher and receiver facilities enabling routine scraping and integrity management.

Build-Ready Package

Coordinated multidisciplinary deliverables — drawings, datasheets and material take-off — ready for procurement and construction.

Six-Month Delivery

Full design and PM scope delivered on a tight six-month programme.

Disciplines Covered

Multidisciplinary by design.

Project ManagementProcessPipingPipeline EngineeringCivil / GradingStructuralInstrumentation & ControlElectrical